Project Overview

Client North China Oilfield
Location Wen’an, Langfang, Hebei Province
Challenge A DN200 crude oil pipeline was at high risk of rupture due to severe flooding, threatening major environmental and operational damage.
Solution Emergency installation of two block valves using hot tap and stopple techniques to enable safe isolation without shutdown.
Results Project completed in 72 hours with zero safety incidents, preventing a potential oil spill and avoiding an estimated $2M+ in production losses.

The Challenge: A Pipeline on the Brink of Failure

In late July 2025, continuous heavy rainfall triggered widespread flooding across Beijing, Tianjin, and Hebei. For North China Oilfield, the crisis was immediate: a DN200 crude oil pipeline in Wen’an was dangerously exposed to floodwaters.

The stakes were immense. Pipeline failure would lead to:

  • Major crude oil spill into floodwaters, worsening an already severe environmental situation.
  • Extended production shutdowns across regional crude networks.
  • Significant safety risks to nearby communities and emergency crews.

The client needed a pipeline emergency repair team that could act fast—without compromising safety or requiring a full system shutdown.

🚨 This was not a routine maintenance case. It was a true emergency pipeline shutdown scenario where every minute counted.


Our pipeline emergency repair team assessing the DN200 crude oil pipeline threatened by severe flooding in Wen'an, highlighting the urgent need for intervention.

Our Solution: Rapid Deployment of Hot Tap & Stopple Technology

Within hours of notification, our 24/7 pipeline emergency response team was mobilized. We proposed a two-phase pipeline emergency repair services plan centered on hot tap and stopple technology—allowing us to install two emergency block valves while the pipeline remained in operation.

Key Technical Measures:

  1. Emergency Block Valve Installation
    • Two full-bore DN200 block valves installed at critical points.
    • Enabled immediate pipeline isolation in case of rupture.
  2. Hot Tapping & Stopple Integration
    • Performed under controlled pressure using certified equipment.
    • Eliminated the need for system-wide shutdown.
  3. Flood-Adapted Construction
    • Portable dewatering systems for continuous pit management.
    • All-weather welding and assembly protocols.
  4. Real-Time Risk Monitoring
    • On-site environmental and pipeline integrity tracking.

🔧 Why This Approach Worked:

  • Zero Production Interruption: The hot tap and stopple method allowed the crude line to remain operational throughout the repair.
  • Safety First: All work complied with international pipeline safety standards (ASME B31.4 / API 1176).
  • Flood-Resistant Logistics: Our team was equipped with amphibious vehicles and mobile water pumps for access to submerged work areas.

Preparing for hot tap and stopple operation: creating a stable work area with continuous dewatering in challenging, waterlogged conditions.
Performing a critical hot tap on the live DN200 pipeline - a key step in our pipeline emergency repair services to install isolation valves without shutdown.

Implementation: 72-Hour Race Against the Floods

Phase 1: Rapid Mobilization (July 26, 22:06 – July 27, 03:04)

  • 22:06: First truck with emergency pipeline repair equipment departs.
  • 00:14: All major equipment en route to Wen’an.
  • 03:04: Excavation and slope preparation completed despite heavy rain.

Phase 2: Critical Valve Installation (July 27, 04:27 – July 29, 12:00)

  • 04:27: Hot tap drilling commenced on live pipeline.
  • 16:30: First block valve successfully installed and pressure-tested.
  • July 28, 14:00: Second valve installation underway amid rising floodwaters.

Phase 3: Final Testing & Commissioning (July 29, 12:00 – 20:20)

  • 20:20: Downstream stopple completed. All systems tested and operational.

🌧️ On-Site Challenges Overcome:

  • Continuous rainfall and floodwater infiltration
  • Night operations with limited visibility
  • Multiple equipment logistics in submerged terrain

Results & Impact: Securing Operations Against Future Disasters

The pipeline emergency repair project delivered measurable outcomes that extended far beyond immediate risk mitigation:

Quantifiable Results:

  • Zero Safety Incidents: Full compliance with all safety protocols despite extreme conditions.
  • 72-Hour Completion: From mobilization to operational readiness.
  • $2M+ in Prevented Losses: Based on client’s production value and potential environmental cleanup costs.
  • 2 Emergency Block Valves: Installed and operational for future security.

Client Testimonial:

“When the floodwaters threatened our primary crude line, we needed a team that could respond immediately with technical expertise. Their pipeline emergency repair services team not only prevented a disaster but did so without shutting down our operations. This was world-class emergency response for oil and gas pipelines.”

— Zhang Wei, Pipeline Operations Manager, North China Oilfield

Long-Term Value:

  • Enhanced Pipeline Resilience: The installed valves now serve as permanent risk mitigation assets.
  • Regional Environmental Protection: Contributed to Xiongan New Area flood defense efforts.
  • Proven Emergency Protocol: This project now serves as a benchmark for flood-related pipeline risk management across China.
Round-the-clock response: our 24/7 pipeline emergency repair services in action, mobilizing equipment and personnel through the night to reach the site.
Our certified welders executing high-integrity welds for the valve assembly, demonstrating expertise in all-weather pipeline emergency repair.
The project team efficiently overcoming logistical hurdles like stuck vehicles, showcasing problem-solving skills essential for successful emergency response.
Successful completion of the pipeline emergency repair services project for North China Oilfield, ensuring operational continuity and environmental protection.

Why Choose Our Pipeline Emergency Repair Services?

This case study exemplifies our core capabilities in emergency pipeline repair:

  • 24/7 Rapid Response: We mobilize within hours, not days.
  • Live-Line Expertise: Hot tap and stopple competency ensures zero production loss.
  • Extreme-Environment Experience: From floods to seismic events, we operate where others cannot.
  • End-to-End Project Management: From risk assessment to commissioning and documentation.

Ready for Pipeline Emergencies?

Don’t wait for a crisis to test your response plan. Contact our pipeline emergency repair services team today for:

  • 📞 24/7 Emergency Hotline
  • 🔧 Pre-Risk Site Assessments
  • 🛠️ Preventive Maintenance Programs

Ensure your operations are protected against the unexpected with experts who have proven results in the most challenging conditions.