High-Pressure Gas Pipeline Relocation and Pressure Isolation Project

HighPressure_GasPipeline_Relocation_Isolation

Project Overview

This high-pressure gas pipeline relocation project involves constructing 551m of new pipeline to replace an existing line. The new route runs:

  1. Eastward along the north side of a new retaining wall (green belt area) to Yuanmenpu Road
  2. Northward along the west sidewalk of Yuanmenpu Road, crossing XB05 Road
  3. Connecting to the existing GA1-class pressure pipeline (design pressure: 6.3 MPa)

Key Construction Details:

  • New Pipeline Specifications:
    • Material: L360M high-frequency straight seam welded steel pipe
    • Dimensions: D355.6×6.3mm
    • Coating: 3PE reinforced anti-corrosion
  • Abandoned Pipeline Protocol: Nitrogen purging + grouting
  • Pressure Isolation Works:
    • 2 live gas line plugging points
    • 4 cold cutting sections
    • 4 buttering wall installations

Technical Parameters:

ParameterValue
DiameterD355.6×6.3mm
Design Pressure6.3 MPa (GA1 Class)
ContentNatural gas
Coating3PE reinforced

Project Timeline & Stakeholders:

  • Client: Hunan Zhongyou Gas Co., Ltd.
  • Duration: November 20 – December 20, 2023
  • Location: Yuci Road, Liling City, Hunan Province
HighPressure_GasPipeline_Relocation_Isolation
HighPressure_GasPipeline_Relocation_Isolation
HighPressure_GasPipeline_Relocation_Isolation
HighPressure_GasPipeline_Relocation_Isolation
HighPressure_GasPipeline_Relocation_Isolation
HighPressure_GasPipeline_Relocation_Isolation
HighPressure_GasPipeline_Relocation_Isolation
HighPressure_GasPipeline_Relocation_Isolation