Live Pipeline Plugging and Replacement for Shenmu-Anping Coalbed Methane (CBM) Pipeline Project

ShenmuAnping_CBM_LivePlugging_Replacement

Project Overview

In September 2021, inline inspection (ILI) of the Xingxian Gas (CBM) Utilization Project and Yuanping Second Gas Source Connection Project revealed critical deformations requiring pipe replacement:

  • 13% OD deformation at 12,189.156m
  • 11.8% OD deformation at 46,632.817m
  • 11.3% OD deformation at 13,012.803m

This non-stop pipeline isolation solution ensures continuous CBM supply during repairs.

ShenmuAnping_CBM_LivePlugging_Replacement
ShenmuAnping_CBM_LivePlugging_Replacement
ShenmuAnping_CBM_LivePlugging_Replacement
ShenmuAnping_CBM_LivePlugging_Replacement

Key Technical Details:

ParameterValue
DiameterФ813×12.5mm
MaterialL450 steel
Design Pressure8.0 MPa
Operating Pressure4.0 MPa
ContentNatural gas
Coating3PE anti-corrosion

Project Timeline & Stakeholders:

  • Client: Huasheng Huifeng Gas Transmission Co., Ltd.
  • Duration: April 24 – July 15, 2022
  • Location: Kelan County, Xinzhou City, Shanxi Province