Projeye Genel Bakış
This offshore gas pipeline isolation project involves pressure containment operations during the relocation of CNOOC’s gas pipeline for the new Fuzhou-Xiamen railway construction. Key tasks include:
Critical Workscope:
- Installation of DN400 full-wrap isolation fittings (4 locations)
- DN400×350 bypass fittings (4 locations)
- DN50 pressure balance lines (4 locations)
- DN400×20 airbag containment fittings (4 locations)
- 150m DN350 bypass pipeline (2 routes)
- Hot tapping operations:
- 4× DN400 isolation taps
- 4× DN350 bypass taps
- 4× DN50 balance taps
- 4× DN200 airbag taps
- Non-sparking pipe cutting (4 locations)
- Plugging operations (8 locations)




Pipeline Specifications:
| Parametre | Değer |
|---|---|
| Çap | φ406×8mm |
| Malzeme | L360M steel |
| Tasarım Basıncı | 4,0 MPa |
| Çalışma Basıncı | 2.0 MPa |
| İçerik | Doğal gaz |
| Kaplama | 3PE korozyon önleyici |
Proje Zaman Çizelgesi ve Paydaşlar:
- Müşteri: China Railway 16th Bureau Group Co., Ltd.
- Süre: June 15 – July 20, 2021
- Konum: Fuzhou City, Fujian Province