Di dời đường ống dẫn khí quan trọng DN400 để phục vụ dự án mở rộng Quốc lộ Fuquan mà không cần ngừng hoạt động

Vận hành thử thiết bị khoan và bịt ống nóng trên đường ống dẫn khí tự nhiên áp suất cao DN400 trong quá trình di dời (Fuzhou, 2023)

Project Spotlight: 

Details
ClientFujian Natural Gas Co., Ltd. (A subsidiary of CNOOC)
LocationCangshan District, Fuzhou City, Fujian Province, China
DateApril 18 – May 18, 2023
Core ChallengeRelocate 1,450 meters of live DN400 natural gas pipeline operating at 4.0 MPa that was obstructed by highway expansion construction, with zero interruption to downstream gas supply and strict adherence to 30-day timeline.
JSW SolutionSegmented live double block and bleed (DBB) hot tapping and plugging technology with temporary bypass installation, executed in two phases across multiple work zones, utilizing JSW proprietary high-pressure equipment and certified welding procedures.
Key ResultComplete pipeline relocation of 1,821.7 meters completed on schedule with 100% gas supply continuity, zero safety incidents, and all welds passing pressure integrity tests, enabling uninterrupted highway construction progress.

The Challenge: A High-Stakes Conflict Between Infrastructure and Energy Supply

In the bustling district of Cangshan, Fuzhou, a major infrastructure upgrade—the widening of the Fuquan Expressway connecting line—posed a direct threat to a vital energy artery. A DN400 natural gas pipeline (Φ406×7.9mm, L415 steel), operating at 4.0 MPa, lay directly in the path of planned interchange ramps and a rotary. Approximately 1,450 meters of this high-pressure pipeline was either encroached upon or situated perilously beneath the footprint of new concrete pile foundations.

For the asset owner, Fujian Natural Gas Co., Ltd., the dilemma was severe. A conventional shutdown-and-relocate approach would mean cutting off gas supply to downstream users for an extended period, resulting in significant commercial losses and community disruption. The pipeline relocation was non-negotiable for the highway project, but the cost of interruption was unacceptable. The client needed a pipeline services contractor capable of executing a live pipeline intervention that guaranteed:

  • Zero supply interruption to end-users.
  • Absolute safety for personnel and the public during construction adjacent to and underneath highway infrastructure.
  • Precise execution on a tight, 30-day timeline to align with the highway construction schedule.
  • Technical excellence in working with high-grade L415 steel and maintaining the integrity of the 3PE coating.
Workers performing hot tapping and plugging on L415 DN400 high-pressure natural gas pipeline during the pipeline relocation project for highway expansion (Fuzhou, 2023)
Crane and workers installing hot tapping & plugging equipment on DN400 L415 natural gas pipeline in the pipeline relocation construction site (Fuzhou, 2023)

The JSW Solution: Precision Engineering with Live Double Block and Bleed Technology

As a specialized pipeline services company and equipment manufacturer, JSW proposed a technically advanced and operationally safe solution: a segmented live hot tapping and plugging operation using the Double Block and Bleed (DBB) method. This approach allowed us to install temporary bypasses and isolate sections of the live line for cutting and tie-in, all while gas continued to flow uninterrupted through the mainline.

Our custom-engineered solution addressed every client concern:

  1. Comprehensive Pre-Engineering Survey & Planning: Before any fieldwork, our engineers conducted a detailed survey alongside the client’s team. We mapped every hot tapping and plugging point (4 points across 2 segments), designed the temporary pipeline bypass installation route, and planned all excavation and shoring for the high-pressure work pits, hot tap pits, and tie-in pits in the challenging urban-soil conditions of Anping and Huji villages.
  2. Deployment of Proprietary Hot Tapping & Plugging Equipment: We utilized JSW-manufactured split-tee fittings, high-pressure tapping machines, and plugging heads specifically rated for the pipeline’s 7.5 MPa design pressure. Our equipment’s reliability was non-negotiable for this live pipeline intervention.
  3. Phased, Risk-Mitigated Execution Plan: The project was strategically divided into two phases—Qingliang Village segment followed by Anping/Huji segment—to manage resources and risk effectively, aligning perfectly with the client’s node.
Workers setting up hot tapping equipment for live intervention on DN400 L415 natural gas pipeline during relocation project (Fuzhou, 2023)
Workers assembling dual block-and-bleed plugging equipment on DN400 high-pressure natural gas pipeline (Fuzhou pipeline relocation project, 2023)

The Execution: A Symphony of Technical Skill and Project Management

The implementation demonstrated JSW’s dual strength as a hands-on contractor and a master project manager.

Phase 1: Qingliang Village Segment (15-Day Sprint)

  • Days 1-7: Upon site handover, our crew immediately executed safe excavation and hydraulic shoring for all critical work pits. Simultaneously, we set up site facilities and prepared the first pipeline section.
  • Day 8: A formal joint construction condition confirmation with the client ensured all safety and technical prerequisites were met—a step that builds trust and prevents errors.
  • Days 9-15: The core hot tapping and plugging sequence began:
    1. Precision Welding: Certified welders performed in-service welding of JSW split-tee fittings onto the live L415 steel pipeline, following stringent procedures to prevent burn-through.
    2. Hot Tapping: Using our tapping machines, we safely drilled into the 4.0 MPa gas stream to create connections for the bypass.
    3. Bypass Installation & Commissioning: A pre-fabricated temporary bypass line was installed and pressurized, becoming the new flow path for the gas.
    4. Plugging & Isolation: Plugging heads were inserted through the tees to create a double block and bleed isolation on the old pipeline section.
    5. Cutting, Tie-in & Restoration: The isolated old pipe section was cut, the new DN400 natural gas pipeline segment was welded in place, and the site was restored. Upon completion, the process was reversed to transfer flow back to the new permanent line.

Phase 2: Anping & Huji Village Segment (15-Day Execution)
Following the same disciplined protocol, our mobilized team replicated the success in the second, more complex area with multiple highway encroachments. The experience gained in Phase 1 allowed for even smoother execution, demonstrating the scalability of our pipeline services.

Preparation for pipeline bypass installation after hot tapping on DN400 natural gas pipeline (highway expansion relocation project, 2023)
Workers conducting multi-point hot tapping & plugging on DN400 L415 natural gas pipeline during relocation construction (Fuzhou, 2023)

Results & Benefits: Quantifiable Success and Strengthened Partnership

The JSW team delivered a textbook example of a complex pipeline relocation for highway expansion. The results speak for themselves:

  • 100% Gas Supply Continuity: Achieved zero interruptions in natural gas delivery to the community and industries throughout the entire pipeline relocation process.
  • Flawless Safety Record: Completed over 1,821 meters of new high-pressure pipeline construction and all live intervention work with zero safety incidents, despite working in confined pits near live traffic.
  • On-Time, On-Budget Delivery: All work was completed within the stringent 30-day window (April 18 – May 18, 2023), ensuring no delays for the critical highway construction project.
  • Technical Excellence Validated: The integrity of all welds and the new pipeline section passed all non-destructive testing (NDT) and pressure tests on the first attempt.

Client Testimonial:
“The highway expansion was on a critical path, and the thought of a pipeline shutdown was untenable. JSW didn’t just offer a service; they provided a guaranteed solution. Their expertise in hot tapping and plugging pipeline technology turned a high-risk problem into a seamless operation. Their team’s professionalism, from engineering to execution, was exceptional. They were a true partner, not just a contractor.”
— Project Manager, Fujian Natural Gas Co., Ltd. (Simulated)

Welding pipe fittings for hot tapping equipment on DN400 L415 high-pressure natural gas pipeline (pipeline relocation site, 2023)
Workers sealing pipe ends after hot tapping & plugging on DN400 natural gas pipeline (highway expansion relocation project, 2023)

About JSW Pipeline Services

JSW is a global leader in specialized pipeline services and an innovative manufacturer of pipeline intervention equipment. We bridge the gap between engineering and execution for the world’s most demanding energy and utility assets.

Our Services Include:

  • Live Pipeline Interventions: Hot Tapping, Plugging, Line Stopping, Pipeline Bypass Installation.
  • Pipeline Modifications: Natural Gas Pipeline Relocation, Replacement, and High-Pressure Pipeline Construction.
  • Emergency Response & Maintenance: Leak Repair, Valve Insertion, Pipeline Integrity Management.

Why Choose JSW?
We combine the hands-on reliability of a top-tier field contractor with the technical precision of an equipment OEM. This unique position allows us to design and execute solutions that are not only effective but also optimally efficient and safe. When you face a challenge involving live pipeline intervention or complex pipeline relocation, partner with the experts who build the tools and master the techniques.

Ready to discuss your pipeline challenge? Contact JSW Pipeline Services today for a confidential consultation.

Yêu cầu tư vấn miễn phí về dịch vụ đường ống

Sẵn sàng hợp tác chưa? Hãy cùng chúng tôi thực hiện một dự án!

Tìm hiểu thêm tại

Bạn đang gặp khó khăn trong việc triển khai dự án đường ống? Hãy nhận giải pháp được thiết kế riêng từ các chuyên gia của chúng tôi. Vui lòng cung cấp thông tin chi tiết của bạn ở bên dưới, và chúng tôi sẽ liên hệ với bạn trong vòng 24 giờ để thảo luận về các yêu cầu dự án, tiến độ và ngân sách của bạn.

Bắc Kinh Jinshiwan là nhà cung cấp tổng hợp hàng đầu về công nghệ và dịch vụ đường ống, kết hợp sản xuất thiết bị cao cấp với chuyên môn kỹ thuật chuyên nghiệp. Chúng tôi cung cấp các giải pháp đường ống an toàn, đáng tin cậy và sáng tạo trong suốt vòng đời cho các ngành công nghiệp dầu khí, hóa chất và tiện ích trên toàn cầu.

Xây dựng và lắp đặt đường ống
  • Xây dựng đường ống xuyên quốc gia
  • Lắp đặt và vận hành thử đường ống
  • Lắp đặt hệ thống đường ống nhà máy
  • Di dời và cải tạo đường ống
  • Dịch vụ khoan lấy mẫu nóng và khoan lấy mẫu dưới áp lực
  • Dịch vụ bịt kín và cách ly đường ống
  • Sửa chữa khẩn cấp đường ống
  • Cải tạo và lót ống dẫn
  • Sửa chữa bằng ống lót composite (lắp đặt ống lót loại B)
  • Bảo vệ chống ăn mòn và sửa chữa
  • Quản lý tính toàn vẹn của đường ống
  • Dịch vụ hỗ trợ kiểm tra trực tuyến
  • Các công việc sửa chữa đường dây điện đang hoạt động mà không gây gián đoạn
  • Thử áp lực đường ống
  • Vệ sinh và sấy khô đường ống
  • Sản xuất máy khoan nóng
  • Sản xuất thiết bị bịt ống dẫn
  • Sản xuất phụ kiện đường ống theo yêu cầu
  • Sản xuất van đặc biệt

• Khả năng ứng phó khẩn cấp 24/7
• Các tiêu chuẩn tuân thủ API và ASME
• Quản lý dự án đa ngôn ngữ
• Hỗ trợ vận chuyển và hậu cần toàn cầu
• Giám sát kỹ thuật tại hiện trường trên toàn thế giới

Các dự án dịch vụ đường ống của JSW

Dịch vụ đường ống

Niềm tin và Giá trị

Khách hàng của chúng tôi