Un dossier complet de taraudage à chaud à haute pression et à haute température pour le projet EPC du terminal GNL de Ningbo 

Pipeline (avec coude) raccordé à un équipement de prélèvement à chaud, avec échafaudage et grue, prêt pour le forage sous pression dans le cadre d'un projet EPC.

Project Snapshot:

CatégorieDétails
ClientInternational Energy Major (EPC Project)
LocalisationNingbo, China
Défi centralExecute 12 hot taps on live, high-pressure (7.0 MPa) natural gas and high-temperature (300°C) thermal oil pipelines made of high-grade steel (X60/L415Q) with thick, non-standard walls, without shutdown.
JSW SolutionCustom-engineered hot tapping services, including design/fabrication of heavy-duty fittings, stringent welding procedures, and deployment of proprietary high-capacity drilling equipment. A full-scope EPC support service.
Principaux résultatsZero shutdowns achieved. 100% success rate on all connections. Flawless safety record. Client’s expansion timeline and continuous production guaranteed.

Project Challenge: Performing “Heart Bypass Surgery” on a Live “Energy Artery”

For any major LNG receiving terminal, its internal pipeline system is a vital “energy artery” where failure is not an option. When our client — a leading international energy company — advanced the third-phase expansion and modification EPC project at its Ningbo Terminal, they faced a critical pipeline modification challenge: adding new connections to live pipelines carrying 300°C thermal oil and high-pressure natural gas (up to 7.0 MPa) without a single shutdown.

A full shutdown would have meant staggering production losses, measured in millions per day. The technical hurdles were formidable:

  • Extreme Parameters: Simultaneous high-temperature (300°C) hot tapping on thermal oil lines and high-pressure (7.0 MPa) hot tapping on gas lines.
  • Demanding Materials: Working on high-grade steel (X60, L415Q) pipelines with non-standard diameters (D717, D660) and extra-thick walls (up to 30mm pipe, 50mm fitting reinforcement).
  • Zero-Margin for Error: Operations were on critical infrastructure where safety and integrity were paramount. Any flaw in welding or the under-pressure drilling process could lead to catastrophic failure.

They needed more than just a contractor; they needed a partner with proven expertise in specialized pipeline hot tapping services capable of handling such a complex EPC scope. That’s where JSW Pipeline Services was engaged.

Red hot tapping equipment (with four-way fitting) being installed on industrial pipeline during EPC pipeline modification project, with workers and lifting gear on site
Pipeline system (with elbow) connected to hot tapping equipment, with scaffolding and crane at EPC pipeline modification site

Our Solution: A Tailored Engineering Protocol for Precision Live Intervention

As a company that is both a specialized pipeline services contractor and a manufacturer of related equipment, JSW approached this not as a standard job, but as an engineered project. Our solution was a multi-layered, custom-designed protocol:

1. Engineered Fitting & Advanced Welding:
We designed and fabricated full-encirclement split tees with 50mm-thick reinforcing pads to manage stress. Our certified welders executed stringent Welding Procedure Specifications (WPS) for X60 and L415Q materials, involving pre-heat, controlled interpass temperature, and Post Weld Heat Treatment (PWHT) where necessary, all monitored and documented to ensure integrity equal to the parent pipe.

2. Proprietary Hot Tapping Equipment:
We deployed our own large-stroke, high-torque hot tapping machines (JSW-HT Series), specifically designed for thick-wall pipeline drilling. These machines feature enhanced stability and cutting tool technology to handle the high-grade steel efficiently and safely under full pressure.

3. Rigorous Risk-Mitigated Execution Plan:
Every hot tap service was preceded by a Job Safety Analysis (JSA) and a detailed “hold point” procedure. Our methodology for under pressure drilling included dual-valve isolation, pilot hole verification, and continuous pressure monitoring throughout the cutting process.

Implementation: Flawless Execution Through Military-Grade Precision

Our role as the specialist EPC pipeline services partner involved seamless integration with the main contractor’s schedule. The key phases were:

  • Phase 1: Fit-for-Purpose Preparation. Site surveys, procedure qualification, and fit-up of custom fittings using laser alignment for perfect orientation.
  • Phase 2: Critical Welding Campaign. Execution of thick-wall welds under controlled conditions, followed by 100% Non-Destructive Testing (NDT) via Ultrasonic Testing (UT) and Radiographic Testing (RT).
  • Phase 3: The Live Tap. Mounting the tapping machine, pressure testing the assembly, and performing the pipeline hot tapping. The drilling of the D717 high-pressure gas line was a pinnacle moment, requiring meticulous control as the cutter penetrated the 19.1mm thick X60 steel under 7.0 MPa.
  • Phase 4: Completion & Handover. Machine retrieval, installation of the completion plug, final testing, and corrosion coating application. All waste (coupons) was safely contained and removed.
Red hot tapping device integrated with industrial pipeline system in EPC pipeline modification project site
Workers operating lifting gear to assist hot tapping equipment installation on high-pressure pipeline during EPC pipeline services

Results & Benefits: Delivering Quantifiable Value Beyond the Task

The success of this pipeline modification service was measured in safety, reliability, and economics.

Quantifiable Outcomes:

  • Zero Safety or Environmental Incidents: Perfect HSE record throughout the project.
  • 100% Operational Continuity: All 12 hot taps were completed without requiring a shutdown, saving the client an estimated multi-million-dollar loss in potential production downtime.
  • 100% Success Rate: All connections were completed on schedule, passed all integrity tests, and are fully operational.
  • Future-Proof Design: The installed tee fittings with internal debris filters ensure no interference with future pipeline inspection gauges (PIGs).

Client Feedback:
“The JSW team managed our most critical pipeline intervention with outstanding professionalism. Their dual capability as equipment makers and field specialists was evident. They engineered solutions for our unique thick-wall, high-pressure taps, not just applied standard tools. Their work ensured our expansion stayed on track without disrupting terminal operations for even a minute.”
— Project Manager, Client EPC Team

Why JSW Pipeline Services is Your Trusted Partner

This Ningbo Terminal project exemplifies the core of JSW. We are not just a service company; we are a technology-integrated contractor. As both manufacturers and practitioners, we control the entire value chain—from designing the right equipment for the job to executing the field work with unparalleled know-how.

Our service portfolio includes:

  • Hot Tapping & Plugging Services: For all diameters, pressures, and media.
  • Pipeline Emergency Response & Repair: 24/7 readiness for urgent interventions.
  • Pipeline Commissioning & Modifications: Supporting EPC projects globally.
  • Preventive Maintenance & Integrity Solutions: Extending asset lifecycles.

We combine engineering excellence with field-proven experience to deliver pipeline solutions that are safe, efficient, and economically superior.

Demander une consultation gratuite sur le service des pipelines

Prêt à travailler ensemble ? Construisez un projet avec nous !

En savoir plus

Vous êtes confronté à un problème de pipeline ? Obtenez une solution sur mesure de la part de nos experts. Indiquez vos coordonnées ci-dessous et nous vous contacterons dans les 24 heures pour discuter des exigences, du calendrier et du budget de votre projet.

Beijing Jinshiwan est un fournisseur intégré de premier plan en matière de technologies et de services liés aux pipelines, qui associe la fabrication d'équipements haut de gamme à une expertise professionnelle en matière d'ingénierie. Nous fournissons des solutions sûres, fiables et innovantes pour l'ensemble du cycle de vie des pipelines aux industries mondiales du pétrole et du gaz, de la chimie et des services publics.

Construction et installation de pipelines
  • Construction de pipelines à travers le pays
  • Installation et mise en service des pipelines
  • Installation des systèmes de canalisation de l'usine
  • Déplacement et modification de pipelines
  • Services de taraudage à chaud et de taraudage sous pression
  • Services d'obturation et d'isolation des pipelines
  • Réparation d'urgence des canalisations
  • Réhabilitation et revêtement de pipelines
  • Réparation d'un manchon composite (installation d'un manchon B)
  • Protection contre la corrosion et réparation
  • Gestion de l'intégrité des pipelines
  • Services de soutien à l'inspection en ligne
  • Modifications de la ligne sous tension sans perturbation
  • Essais sous pression des pipelines
  • Nettoyage et séchage des canalisations
  • Fabrication de machines à tarauder à chaud
  • Production d'équipements d'obturation de pipelines
  • Fabrication de raccords de tuyauterie sur mesure
  • Fabrication de vannes spéciales

- Capacité d'intervention d'urgence 24 heures sur 24 et 7 jours sur 7
- Normes API et ASME
- Gestion de projets multilingues
- Expédition et soutien logistique à l'échelle mondiale
- Supervision technique sur place dans le monde entier

JSW Pipeline Service Projects

Service des pipelines

Confiance et valeur

Nos clients