Taixing Chengdong Industrial Park High-Pressure Gas Pipeline Non-Stop Relocation Project: A Case Study in Zero-Downtime Pipeline Maintenance

Professional project planning and safety setup for the Taixing DN400 pipeline relocation, showcasing our commitment to zero-incident hot tapping and plugging services.

Project Overview Summary

Client: Taixing Xin’ao Gas Co., Ltd.
Location: Taixing City, Jiangsu Province, China
Contractor: Công ty TNHH Công nghệ Đường ống Jinshiwan Bắc Kinh.
Project Challenge: Relocating 156 meters of critical DN400 high-pressure natural gas pipeline (4.0MPa) serving an industrial park without interrupting gas supply
Solution: Comprehensive hot tapping and line plugging services with temporary bypass system
Key Results: Completed within 30-day timeline with zero safety incidents and continuous gas supply throughout the project

The Critical Challenge: Maintaining Industrial Gas Supply During Essential Pipeline Relocation

When Taixing Xin’ao Gas Company faced the necessity of relocating 156 meters of critical DN400 high-pressure natural gas pipeline in the bustling Chengdong Industrial Park, they confronted a seemingly impossible dilemma. This high-pressure gas pipeline maintenance operation served numerous manufacturing facilities that depended on uninterrupted natural gas supply for their operations. A traditional shutdown would have caused:

  • Production stoppages across multiple industrial plants
  • Estimated economic losses exceeding millions of yuan daily
  • Potential safety risks associated with complete depressurization and repressurization
  • Extended downtime affecting regional economic activity

The technical specifications added further complexity: the 4.0MPa design pressure and DN400 pipeline diameter represented significant engineering challenges for any non-stop pipeline repair operation. The client needed a solution that would allow the pipeline relocation while maintaining continuous gas flow to downstream consumers.

hot-tapping-service-preparation-taixing-industrial-park-dn400-pipeline
A certified welder precisely welds a DN400 hot tapping fitting onto the 4.0MPa live gas main, a critical first step for pipeline plugging.

Our Customized Solution: Advanced Hot Tapping and Line Plugging Technology

Beijing Jinshiwan Pipeline Technology developed a comprehensive pipeline relocation services package centered around advanced hot tapping and line plugging services. Our solution combined decades of experience in high-pressure pipeline engineering with state-of-the-art equipment and methodology.

Technical Approach Overview:

Our engineered solution involved a multi-phase approach to ensure safety and continuity:

  1. Temporary Bypass System Installation: Designing and implementing a DN300 temporary bypass line to maintain gas flow during the critical cutting and connection phases

  2. Four-Point Isolation Strategy: Executing simultaneous hot tapping and line plugging at four separate locations to create isolated sections for safe modification

  3. Pressure Equalization Technology: Implementing DN50 pressure balance connections to ensure safe plugging head operation under 4.0MPa pressure conditions

  4. Butterwall Construction: Building two specialized butterwall barriers as additional safety measures at critical connection points

Our pipeline plugging services utilized equipment specifically rated for the 4.0MPa operating pressure, with all DN400 pipeline fittings undergoing rigorous testing and certification before deployment. The technical implementation represented some of the most challenging pipeline maintenance solutions in the industry due to the combination of diameter, pressure, and operational criticality.

Implementation Excellence: Precision Execution Under Pressure

The successful implementation of these hot tapping and line plugging services required meticulous planning and flawless execution. Our certified pipeline technicians followed a rigorously tested procedure:

Phase 1: Preparatory Work and Bypass Installation

  • Site preparation and safety perimeter establishment
  • Installation of temporary DN300 bypass piping with full pressure testing
  • Welding of hot tapping fittings and pipeline plugging fittings at all four locations

Phase 2: Hot Tapping Operations

  • Execution of 8 separate hot tapping operations (4×DN50 and 4×DN400)
  • Installation of pipeline plugging equipment and pressure testing of all connections
  • Comprehensive leak testing of all mechanical connections

Phase 3: Line Stopping and Pipeline Modification

  • Activation of pipeline plugging heads to isolate sections for modification
  • Verification of plugging head seal integrity under full operating pressure
  • Execution of non-stop pipeline cutting and connection of new pipeline sections
  • Construction of butterwall barriers at critical junctions

Phase 4: System Restoration and Testing

  • Deactivation of plugging equipment and restoration of flow through main pipeline
  • Disconnection and removal of temporary bypass system
  • Hydrostatic testing and pipeline commissioning
  • Comprehensive documentation and client handover

Throughout the 30-day project timeline, our team maintained strict adherence to industrial safety standards while implementing these complex pipeline intervention services.

hot-tapping-machine-operation-dn400-natural-gas-pipeline
Technicians configure the advanced line plugging head assembly prior to insertion into the pipeline for isolation.

Quantifiable Results and Client Benefits

The successful completion of this challenging pipeline relocation project delivered significant measurable benefits to Taixing Xin’ao Gas Company:

Operational and Safety Outcomes:

  • Zero supply interruptions to downstream industrial customers throughout the project
  • 100% safety record with no incidents or environmental releases
  • Completion within the 30-day project timeline despite technical complexities
  • All pipeline connection points tested to exceed original design specifications

Economic Impact:

  • Eliminated production losses for industrial customers estimated at over 20 million yuan
  • Avoided emergency response costs associated with traditional shutdown methods
  • Extended pipeline service life with new sections featuring enhanced corrosion protection

Client Testimonial:

“Beijing JSW’s expertise in hot tapping and line plugging services was instrumental to our project’s success. Their ability to maintain gas flow while relocating a critical high-pressure pipeline prevented massive economic disruption to our industrial customers. Their technical team demonstrated exceptional professionalism and problem-solving capabilities throughout the project.”
— Project Manager, Taixing Xin’ao Gas Co., Ltd.

Why Choose Beijing Jinshiwan for Your Pipeline Challenges?

This Taixing Industrial Park project exemplifies our core capabilities in delivering complex pipeline engineering solutions under challenging conditions. Our hot tapping and line plugging services division specializes in:

  • High-pressure pipeline interventions up to 10MPa operating pressure
  • Large-diameter pipeline plugging services for DN50 to DN1000 pipelines
  • Emergency pipeline repair capabilities with rapid response teams
  • Non-stop pipeline modification services for various industries including oil, gas, and chemical sectors
  • Comprehensive pipeline maintenance solutions from planning through execution

Contact Our Pipeline Solutions Team

Facing similar challenges with your pipeline infrastructure? Our team of certified pipeline engineers is ready to develop customized hot tapping and line plugging services for your specific requirements.

Contact Beijing JSW Pipeline Technology today to schedule a consultation and discover how our non-stop pipeline maintenance solutions can protect your operations while enabling essential infrastructure modifications.

Yêu cầu tư vấn miễn phí về dịch vụ đường ống

Sẵn sàng hợp tác chưa? Hãy cùng chúng tôi thực hiện một dự án!

Tìm hiểu thêm tại

Bạn đang gặp khó khăn trong việc triển khai dự án đường ống? Hãy nhận giải pháp được thiết kế riêng từ các chuyên gia của chúng tôi. Vui lòng cung cấp thông tin chi tiết của bạn ở bên dưới, và chúng tôi sẽ liên hệ với bạn trong vòng 24 giờ để thảo luận về các yêu cầu dự án, tiến độ và ngân sách của bạn.

Bắc Kinh Jinshiwan là nhà cung cấp tổng hợp hàng đầu về công nghệ và dịch vụ đường ống, kết hợp sản xuất thiết bị cao cấp với chuyên môn kỹ thuật chuyên nghiệp. Chúng tôi cung cấp các giải pháp đường ống an toàn, đáng tin cậy và sáng tạo trong suốt vòng đời cho các ngành công nghiệp dầu khí, hóa chất và tiện ích trên toàn cầu.

Xây dựng và lắp đặt đường ống
  • Xây dựng đường ống xuyên quốc gia
  • Lắp đặt và vận hành thử đường ống
  • Lắp đặt hệ thống đường ống nhà máy
  • Di dời và cải tạo đường ống
  • Dịch vụ khoan lấy mẫu nóng và khoan lấy mẫu dưới áp lực
  • Dịch vụ bịt kín và cách ly đường ống
  • Sửa chữa khẩn cấp đường ống
  • Cải tạo và lót ống dẫn
  • Sửa chữa bằng ống lót composite (lắp đặt ống lót loại B)
  • Bảo vệ chống ăn mòn và sửa chữa
  • Quản lý tính toàn vẹn của đường ống
  • Dịch vụ hỗ trợ kiểm tra trực tuyến
  • Các công việc sửa chữa đường dây điện đang hoạt động mà không gây gián đoạn
  • Thử áp lực đường ống
  • Vệ sinh và sấy khô đường ống
  • Sản xuất máy khoan nóng
  • Sản xuất thiết bị bịt ống dẫn
  • Sản xuất phụ kiện đường ống theo yêu cầu
  • Sản xuất van đặc biệt

• Khả năng ứng phó khẩn cấp 24/7
• Các tiêu chuẩn tuân thủ API và ASME
• Quản lý dự án đa ngôn ngữ
• Hỗ trợ vận chuyển và hậu cần toàn cầu
• Giám sát kỹ thuật tại hiện trường trên toàn thế giới

Các dự án dịch vụ đường ống của JSW

Dịch vụ đường ống

Niềm tin và Giá trị

Khách hàng của chúng tôi