Déplacement de précision d'un pipeline pour le train à grande vitesse de Xiongshang, garantissant l'absence d'arrêt de production

Les ingénieurs de Jinshiwan effectuent une étude de terrain préalable à la construction afin de vérifier les matériaux et l'état des pipelines, une première étape cruciale pour la réussite du projet.

Project Overview at a Glance

  • Client : Sichuan Renshengxin Construction Co., Ltd. (on behalf of the asset owner, Huabei Oilfield)
  • Localisation : Shenzhou, Hebei Province, China
  • Défi : Relocate a high-pressure crude oil pipeline obstructing a critical high-speed rail foundation without stopping production, avoiding massive financial loss and safety risks.
  • Solution : A meticulously planned in-service pipeline modification using hot tapping and stoppling technology to bypass the section, followed by a safe pipeline tie-in.
  • Results: Successfully completed with zero safety incidents, zero production interruption, and ahead of the tight construction schedule.

The Critical Challenge: A High-Stakes Intersection of Energy and Infrastructure

The monumental Xiongshang High-Speed Rail project, a vital artery in China’s transport network, faced a significant obstacle in its Shenzhou section. The proposed foundation (Pile Cap 65) for the rail line was in direct conflict with an active, high-pressure crude oil pipeline—the Shen-Chu transmission line.

For pipeline construction companies and infrastructure developers, this scenario represents a classic but high-risk problem:

  • Immense Financial Pressure: A shutdown of the pipeline for traditional relocation was not an option. The cost of halting crude oil flow—in terms of lost production, supply chain disruption, and contractual penalties—would have been astronomical for the owner, Huabei Oilfield.

  • Significant Safety Risks: The pipeline operated at a high design pressure of 6.3MPa. Any work involving “live” crude oil pipelines carries inherent risks of leaks, fires, or explosions, especially during cutting and welding phases. The proximity to ongoing high-speed rail construction activities amplified these risks.

  • Engineering Precision: The new 227-meter section of Φ219*7.1mm pipeline had to be installed with perfect alignment and integrity to ensure long-term operational safety and efficiency, matching the exact specifications of the existing line.

The client, Sichuan Renshengxin Construction, needed a pipeline engineering contractor with proven expertise in handling such sensitive, high-stakes operations. They turned to Beijing Jinshiwan Pipeline Technology for a solution.

    Overview of the worksite where the crude oil pipeline conflicted with the Xiongshang high-speed rail foundation construction.
    Jinshiwan technicians carefully aligning and welding the new Φ219*7.1mm pipeline section for the relocation.

    Our Tailored Solution: Engineering a Safer, Smarter Bypass

    Our approach was rooted in a fundamental principle: eliminate the risk by never exposing the live pipeline. We designed and executed a custom in-service pipeline modification plan centered on hot tapping and stoppling.

    Here’s a breakdown of our technical solution:

    1. Comprehensive Pre-Construction Survey: Before fabrication, our team conducted an on-site verification of pipe material, exact length, and surrounding environment. This crucial step, as stipulated in our contract, ensured all materials and plans were perfectly tailored to real-world conditions, preventing costly delays.

    2. The Bypass Installation: We first installed the new 227-meter bypass section, meticulously welding and testing it according to the strictest quality standards, while the original pipeline remained fully operational.

    3. Hot Tapping & Stoppling – The Core of Zero Downtime:

      • Taraudage à chaud : Using specialized equipment, we safely drilled into the live pipeline at two designated points to create connections for the bypass. This process is done without leaking a single drop of oil, thanks to pressure-sealing technology.

      • Stoppling: Following the taps, we inserted sealing heads (stopples) into the pipeline. These devices temporarily blocked the flow of oil through the old section, diverting it seamlessly through the new bypass line we had just installed.

    4. Safe Tie-In and Commissioning: With the flow safely diverted, the isolated section obstructing the rail construction was removed. The final, critical phase was the pipeline tie-in—the permanent welding of the new section into the main line. This was conducted under strictly controlled conditions, with comprehensive safety measures in place. Once tested and verified, the stopples were removed, and the pipeline was returned to its normal flow path through the new route, ready for operation.

    Specialized hot tapping machine performing a connection on the live, high-pressure crude oil pipeline without shutdown.
    Precise insertion of a stoppling head to temporarily divert oil flow during the in-service pipeline modification.

    The Execution: Meticulous Planning Meets Flawless Implementation

    Our reputation as a leading provider of oil and gas pipeline services is built on our methodical project management. For this project, execution was key:

    • Phased Workflow: The project followed a strict sequence: Bypass Installation → Hot Tapping → Flow Diversion (Stoppling) → Old Section Removal → Final Tie-In → System Commissioning.

    • Safety-First Protocol: Every team member was drilled in emergency procedures. The worksite was secured, and all hot work was conducted under permits and continuous atmospheric monitoring.

    • Seamless Collaboration: We worked in close coordination with Sichuan Renshengxin Construction and the asset owner, ensuring our work integrated perfectly with the overall high-speed rail construction timeline.

    Quantifiable Results & Lasting Benefits

    The success of this project is measured in hard data and client satisfaction.

    • 100% Temps de disponibilité maintenu : Achieved the primary goal of zero interruption to the crude oil transmission, safeguarding the client’s revenue and operational continuity.

    • Un bilan de sécurité irréprochable : Completed the complex pipeline relocation and hot tapping operations with zero accidents or environmental incidents.

    • Respect des délais : All work was completed efficiently, ensuring no delays to the critical path of the high-speed rail project.

    • Intégrité des infrastructures à long terme : The newly installed section ensures the safe, reliable operation of the oil pipeline for decades to come, coexisting securely with the new rail infrastructure.

    Témoignage d'un client :
    “The complexity of working on a live high-pressure pipeline next to a national-level infrastructure project cannot be overstated. Beijing Jinshiwan’s expertise was the differentiator. Their methodical approach and mastery of hot tapping and stoppling technology gave us absolute confidence. They delivered a perfect safety and operational record, turning a major project risk into a resounding success.”
    — Project Manager, Sichuan Renshengxin Construction Co., Ltd.

    Our technician operating a hot tapping machine drilling into the 6.3MPa live crude oil pipeline, the core of our zero-shutdown solution.

    This project for the Xiongshang High-Speed Rail is a testament to how technical expertise can solve complex industrial challenges. For pipeline construction companies and asset owners facing the dilemma of maintaining flow while modifying infrastructure, in-service pipeline modification is not just an option—it’s the most reliable and economical solution.

    Is your next project facing a similar challenge with a critical pipeline?

    Contact Beijing Jinshiwan Pipeline Technology today. Let our experience become your advantage.

    Demander une consultation gratuite sur le service des pipelines

    Prêt à travailler ensemble ? Construisez un projet avec nous !

    En savoir plus

    Vous êtes confronté à un problème de pipeline ? Obtenez une solution sur mesure de la part de nos experts. Indiquez vos coordonnées ci-dessous et nous vous contacterons dans les 24 heures pour discuter des exigences, du calendrier et du budget de votre projet.

    Beijing Jinshiwan est un fournisseur intégré de premier plan en matière de technologies et de services liés aux pipelines, qui associe la fabrication d'équipements haut de gamme à une expertise professionnelle en matière d'ingénierie. Nous fournissons des solutions sûres, fiables et innovantes pour l'ensemble du cycle de vie des pipelines aux industries mondiales du pétrole et du gaz, de la chimie et des services publics.

    Construction et installation de pipelines
    • Construction de pipelines à travers le pays
    • Installation et mise en service des pipelines
    • Installation des systèmes de canalisation de l'usine
    • Déplacement et modification de pipelines
    • Services de taraudage à chaud et de taraudage sous pression
    • Services d'obturation et d'isolation des pipelines
    • Réparation d'urgence des canalisations
    • Réhabilitation et revêtement de pipelines
    • Réparation d'un manchon composite (installation d'un manchon B)
    • Protection contre la corrosion et réparation
    • Gestion de l'intégrité des pipelines
    • Services de soutien à l'inspection en ligne
    • Modifications de la ligne sous tension sans perturbation
    • Essais sous pression des pipelines
    • Nettoyage et séchage des canalisations
    • Fabrication de machines à tarauder à chaud
    • Production d'équipements d'obturation de pipelines
    • Fabrication de raccords de tuyauterie sur mesure
    • Fabrication de vannes spéciales

    - Capacité d'intervention d'urgence 24 heures sur 24 et 7 jours sur 7
    - Normes API et ASME
    - Gestion de projets multilingues
    - Expédition et soutien logistique à l'échelle mondiale
    - Supervision technique sur place dans le monde entier

    JSW Pipeline Service Projects

    Service des pipelines

    Confiance et valeur

    Nos clients